An activewear brand selling online, wholesale and in its own stores
Where they started
About forty recurring reports ran the business across nine teams, built and kept up by the people who used them. The raw material came from saved searches in the ERP, ecommerce exports and the attribution tool. The workbooks fed each other: the demand plan read the daily sales file, and the supply plan read the demand plan.
What was settled before the build
Discovery ran as interviews with each team, nine sessions in all. It ended with the 19 sources in scope, the reports each team needed first, the manual workflows the build would retire, and a fixed price for the build. Niche sources and a full P&L went into a second phase, to be scoped once the first one landed.
How the build was sequenced
- Platform: ERP access, then the warehouse, the loader and the modeling layer in place.
- Sources: 17 of the 19 sources in scope landing, among them the ERP, ecommerce, accounting, the ad platforms, email, web analytics, the helpdesk, reviews and returns.
- First tie-out: the first report tied back to its owner's workbook.
- Production: production models and a nightly run.
- Onboarding: each team onboarded to its own reports.
- At handover: about 30 reports built for eight teams.
The scale
- About 4 billion rows in the warehouse, three-quarters of a terabyte, with about ten years of ERP and ecommerce history.
- About 2.5 billion rows in the initial load, then about 120 million new rows a month.
- 145 custom models, about 600 models built every night, nearly 500 tests, and nearly half a terabyte processed on each nightly run.
- 166 governed topics carrying about 5,000 dimensions and measures, and 54 editable input tables.
What the tie-outs caught
Each new report was tied back to its owner's workbook, cell by cell, before it was signed off. Along the way, the checks caught:
- A promo code counted five times over.
- The ERP's own remaining-quantity formula giving the wrong answer.
- About a quarter of paid spend invisible at the ad level. Coverage went from 84 to 99.9 percent.
- A vendor data package inflating gross sales by roughly 30 percent.
Online revenue tied to the old workbook within 0.06 percent for the month and 0.2 percent on any given day, and wholesale tied exactly.
Keeping the platform bill small
The models draw on under a tenth of the roughly 4,400 raw tables available. The ERP alone offered more than 3,500 tables, and fewer than 100 were kept in sync. Billable rows dropped by a quarter in one month, and the nightly run finished in under ten minutes.
What the build put in place
Report owners got 54 editable input tables, and about thirty datasets were opened for self-serve analysis. Access was scoped by department, every report had a plain-language guide, and alerts went to the team's own people when a sync fell behind. Nearly 500 tests ran every night.